[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107661":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107661,783,1,"单选题","某建设工程施工过程中，由发包人供应的材料没有及时到货，导致承包人的工人窝工5个工作日，窝工工日单价200元；承包人租赁的一台挖土机窝工5个台班，台班租赁费500元；承包人自卸汽车窝工2个台班，该自卸汽车折旧费每台300元，工作时燃油动力费每台班80元。则承包人可以索赔的费用是（ ）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2500",false,{"key":16,"text":17,"correct":14},"B","3500",{"key":19,"text":20,"correct":14},"C","4260",{"key":22,"text":23,"correct":24},"D","4100",true,"本题考查索赔费用的组成与计算。由于发包人供应的材料没有及时到货，属于承包人可以索赔的事项。在索赔费用的组成中，承包人自有机械设备的窝工，只能计算折旧费（在工作时，才需要发生的燃油动力费用等，不能索赔）。因此，承包人可以索赔的费用＝200×5（工日）＋500×5（台班）＋300×2（台班）＝4100（元）。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]