[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107659,783,1,"单选题","关于最终结清的阐述中，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量保修期终止后，承包人应按照合同约定向发包人提交最终结清支付申请",false,{"key":16,"text":17,"correct":14},"B","发包人收到最终结清支付申请后的7天内予以核实",{"key":19,"text":20,"correct":21},"C","发包人应在签发最终结清支付证书后的14天内，向承包人支付",true,{"key":23,"text":24,"correct":14},"D","承包人被扣留的质量保证金不足以扣减发包人工程缺陷修复费用的，按争议解决方式处理","考点:最终结清。缺陷责任期终止后，承包人应按照合同约定向发包人提交最终结清支付申请（A的质量保修期，有误）；发包人收到最终结清支付申请后的14天内予以核实（B的7天，有误）；承包人被扣留的质量保证金不足以扣减发包人工程缺陷修复费用的，承包人应承担不足部分的补偿责任（D的按争议解决方式处理，有误）。参见教材P205。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]