[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107658,783,1,"单选题","某钢筋混凝土结构分项工程，某月份的计划单价和计划工程量分别为350元\u002Fm3和3000m3，该月份的实际单价和实际完成工程量分别为360元\u002Fm3和3200m3。则利用赢得值法计算出的该月份混凝土工程的投资绩效指数（CPI）为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.97",true,{"key":16,"text":17,"correct":18},"B","1.03",false,{"key":20,"text":21,"correct":18},"C","1.06",{"key":23,"text":24,"correct":18},"D","0.94","考点:赢得值法。根据相应的计算公式并结合题意，可以算出投资绩效指数（CPI）＝已完工作预算投资（3200×350）\u002F已完工作实际投资（3200×360）＝112\u002F115.2＝0.97，表示投资超支。同理，可以算出进度绩效指数（SPI）＝已完工作预算投资（3200×350）\u002F计划工作预算投资（3000×350）＝112\u002F105＝1.07，表示进度提前。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]