[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107657,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），签约合同中的暂估材料在确定单价以后，其相应项目综合单价的处理方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在综合单价中用确定单价代替原暂估价，并调整企业管理费，不调整利润",false,{"key":16,"text":17,"correct":14},"B","在综合单价中用确定单价代替原暂估价，并调整企业管理费和利润",{"key":19,"text":20,"correct":14},"C","综合单价不做调整",{"key":22,"text":23,"correct":24},"D","在综合单价中用确定单价代替原暂估价，不涉及企业管理费和利润",true,"考点:暂估价。暂估材料或工程设备的单价确定后，如果合同履行过程中价格发生变化，在综合单价中只应取代原暂估单价，不应涉及企业管理费或利润等其他费用的变动。参见教材P171。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]