[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107654,783,1,"单选题","某钢筋混凝土结构分项工程，某月份的计划单价和计划工程量分别为350元\u002Fm3和3000m3，该月份的实际单价和实际完成工程量分别为360元\u002Fm3和3200m3。则利用赢得值法计算出的该月份混凝土工程的投资偏差和进度偏差分别为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超支3.2万元、超前7万元",true,{"key":16,"text":17,"correct":18},"B","超支3.2万元、拖后7万元",false,{"key":20,"text":21,"correct":18},"C","节约3.2万元、拖后3万元",{"key":23,"text":24,"correct":18},"D","节约3.2万元、超前3万元","考点:赢得值法。根据相应的计算公式并结合题意，则有投资偏差（CV）＝已完工作预算投资（3200×350）－已完工作实际投资（3200×360）＝112－115.2＝－3.2（万元），即实际投资超支3.2（万元）；进度偏差（SV）＝已完工作预算投资（3200×350）－计划工作预算投资（3000×350）＝112－105＝7.0（万元），即实际进度提前于计划。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]