[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107653":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107653,783,1,"单选题","投资偏差分析的赢得值法中，已完工作预算投资（BCWP）是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完成工作量×预算单价",true,{"key":16,"text":17,"correct":18},"B","计划工作量×预算单价",false,{"key":20,"text":21,"correct":18},"C","已完成工作量×实际单价",{"key":23,"text":24,"correct":18},"D","计划工作量×实际单价","考点:赢得值法。根据相关概念及公式，A选项符合题意。同时注意，除D没有特定经济含义外，B、C选项，分别表示计划工作预算投资和已完工程实际投资。参见教材P208。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]