[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107652,783,1,"单选题","某工程分项所采用的甲种材料的施工期间实际单价、基准单价、投标单价依次为424元\u002Fm2、400元\u002Fm2、380元\u002Fm2，若风险系数为5%。则调整后的综合单价为（ ）元\u002Fm2。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","400",false,{"key":16,"text":17,"correct":14},"B","390",{"key":19,"text":20,"correct":21},"C","384",true,{"key":23,"text":24,"correct":14},"D","380","考点:物价变化。调整后的综合单价=380+[424-400×（1+5%）]=384元\u002Fm2。参见教材P168。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]