[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107651,783,1,"单选题","施工过程中，发包人要求提前竣工并征得承包人同意、商定相关措施、修订进度计划后，其提前竣工或赶工补偿费用，不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","新增加投入人工的报酬",false,{"key":16,"text":17,"correct":14},"B","不经济使用人工和机械而增加的费用",{"key":19,"text":20,"correct":21},"C","赶工引起的企业管理费增加",true,{"key":23,"text":24,"correct":14},"D","材料提前交货可能增加的费用以及材料运输费的增加","考点:提前竣工（赶工补偿）。赶工费用主要包括：（1）人工费增加：如新增加投入人工的报酬，不经济使用人工的补贴等；（2）材料费增加：可能造成不经济使用材料而损耗过大，材料提前交货可能增加的费用以及材料运输费的增加等；（3）机械费增加：可能增加机械设备投入，不经济使用机械等。参见教材P173。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]