[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107649,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），在合同履行期间，由于招标工程量清单缺项，新增了分部分项工程量清单项目，关于其合同价款确定的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新增清单项目的综合单价应当由监理工程师提出",false,{"key":16,"text":17,"correct":18},"B","新增清单项目导致新增措施项目的，承包人应将新增措施项目施工方案提交发包人批准",true,{"key":20,"text":21,"correct":14},"C","新增清单项目综合单价应由承包人提出，但相关措施项目费用不能再做调整",{"key":23,"text":24,"correct":14},"D","新增清单项目应当额外工程处理，承包人可选择或者不做","考点:工程量清单缺项。新增分部分项工程量清单项目后，引起措施项目发生变化的，应按照规范中工程变更相关规定，在承包人提交的实施方案被发包人批准后调整合同价款。参见教材P164。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]