[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107648,783,1,"单选题","某工程分项的招标工程量清单为1000m2，施工中由于涉及变更实际完成的工程量调整为1200m2。该分项工程招标控制价单价为300元\u002Fm2，投标报价单价为360元\u002Fm2，投标报价浮动率为5%。则根据《计价规范》，该分项工程的超过15%以上部分的单价应为（ ）元\u002Fm2。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","242.25",false,{"key":16,"text":17,"correct":14},"B","300",{"key":19,"text":20,"correct":21},"C","345",true,{"key":23,"text":24,"correct":14},"D","360","考点:工程量偏差。新综合单价=300×（1+15%）=345元\u002Fm2。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]