[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107647,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），工程变更引起施工方案改变并使措施项目发生变化时，承包人提出调整措施项目费用的，应事先将（ ）提交发包人确认。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟实施的施工方案",true,{"key":16,"text":17,"correct":18},"B","索赔意向通知",false,{"key":20,"text":21,"correct":18},"C","拟申请增加的费用明细",{"key":23,"text":24,"correct":18},"D","工程变更的内容","考点:工程变更价款的确定方法。根据《计价规范》，工程变更引起施工方案改变并使措施项目发生变化时，承包人提出调整措施项目费的，应事先将拟实施的方案（A）提交发包人确认，并应详细说明与原方案措施项目相比的变化情况。参见教材P176。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]