[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107646,783,1,"单选题","在工程变更价款的确定中，材料、施工工艺和方法相似，不增加关键线路上工程的施工时间，其项目单价应当（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接采用适用项目的单价",false,{"key":16,"text":17,"correct":18},"B","参考类似的项目单价，由双方协商确定新的项目单价",true,{"key":20,"text":21,"correct":14},"C","采用招标投标时的基础资料和信息价格，按照成本加利润的原则，由双方协商确定新的综合单价",{"key":23,"text":24,"correct":14},"D","由双方协商确定","考点:工程变更价款的确定方法。釆用适用的项目单价的前提是其采用的材料、施工工艺和方法基本类似，不增加关键线路上工程的施工时间，可仅就其变更后的差异部分，参考类似的项目单价由承发包双方协商新的项目单价。参见教材P176。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]