[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107643,783,1,"单选题","某混凝土工程招标清单工程量为200m3，综合单价为300元\u002Fm3。在施工过程中，由于工程变更导致实际完成工程量为160 m3。合同约定当实际工程量减少超过15%时可调整单价，调价系数为1.1。该混凝土工程的实际工程费用为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4.80",false,{"key":16,"text":17,"correct":14},"B","4.89",{"key":19,"text":20,"correct":21},"C","5.28",true,{"key":23,"text":24,"correct":14},"D","6.00","考点:工程量偏差。工程量偏差，可能导致单价变化，进而影响工程价款的结算（增加超过15%，超过部分的单价调低；减少超过15%，所有剩余部分的单价调高）。本混凝土工程的工程量偏差=（160-200）\u002F200=-20%＞15%，其综合单价应予调高。于是，该混凝土工程的实际工程费用=160×300×1.1=52800（元）=5.28（万元）。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]