[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107641,783,1,"单选题","某工程分项的清单工程量为1500m3，因变更实际完成工程量为1200m3；该项目的招标控制价的综合单价为400元\u002Fm3，投标报价的综合单价为420元\u002Fm3，投标报价浮动率为5%，则其结算工程款应当为（ ）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","480000",false,{"key":16,"text":17,"correct":18},"B","504000",true,{"key":20,"text":21,"correct":14},"C","600000",{"key":23,"text":24,"correct":14},"D","630000","考点:工程量偏差。首先，计算该项目实际完成与清单工程量的偏差＝（1200-1500）\u002F1500×100%＝－20%＞15%；其次，根据公式，投标报价的单价P0＝420＞P2×（1－L）×（1－0.15）＝400×95%×0.85＝323，P0＝420＜P2×（1＋0.15）＝400×1.15＝460，故其单价不予调整；最后，计算其应结算的工程价款＝1200×420＝504000（元）。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]