[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107640,783,1,"单选题","采用工程量清单计价的工程在竣工结算时，暂估价中的工程设备单价，应按（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包方自行购买该材料的单价计入综合单价确定",false,{"key":16,"text":17,"correct":18},"B","发、承包双方最终确认价在综合单价中调整",true,{"key":20,"text":21,"correct":14},"C","招标文件中的暂估价定",{"key":23,"text":24,"correct":14},"D","市场价格信息在综合单价中调整","本题考查竣工结算的编制与审查。暂估价中的工程设备单价，应按发、承包双方最终确认价在综合单价中调整。参见教材P202。 新版教材习题陆续更新 金考典考试软件 www.jinkaodian.com",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]