[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107639,783,1,"单选题","竣工结算计价时，依据双方确认的工程量和已标价工程量清单的综合单价计算，是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分部分项工程",false,{"key":16,"text":17,"correct":14},"B","措施项目",{"key":19,"text":20,"correct":14},"C","总价措施项目",{"key":22,"text":23,"correct":24},"D","分部分项工程和单价措施项目",true,"考点:竣工结算的编制与审查。竣工结算计价时，分部分项工程和单价措施项目依据双方确认的工程量和已标价工程量清单的综合单价计算；如果发生调整，执行双方确认调整的单价。参见教材P202。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]