[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107638,783,1,"单选题","根据《计价规范》的规定，承包人应发包人的要求，采取加快工程进度的措施，使合同工程工期缩短产生的，应由发包人支付的费用，该费用属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提前竣工（赶工）费",true,{"key":16,"text":17,"correct":18},"B","施工索赔",false,{"key":20,"text":21,"correct":18},"C","误期赔偿费",{"key":23,"text":24,"correct":18},"D","暂列金额","考点:提前竣工（赶工补偿）。题干所指属于“提前竣工（赶工）费”（A选项）。而且，招标人应依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，超过者，应在招标文件中明示增加赶工费用；施工过程，发包人要求提前竣工的，应征得承包人同意，并应承担提前竣工（赶工补偿）费用。参见教材P173。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]