[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107637,783,1,"单选题","某工程合同约定，承包工程合同总额为3000万元，预付款按照合同总额的10%支付，其中主要材料及构件所占比重为60%，工程预付款从未施工工程尚需的主要材料及设备费相当于工程预付款数额时起扣。则该工程的起扣点是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","300",false,{"key":16,"text":17,"correct":14},"B","500",{"key":19,"text":20,"correct":21},"C","2500",true,{"key":23,"text":24,"correct":14},"D","3000","考点:预付款。预付款为3000×10%＝300万元；T＝P－M\u002FN＝3000－300\u002F60%＝2500。参见教材P195。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]