[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107636,783,1,"单选题","下列关于工程进度款的说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度款支付周期，应与合同约定的工程计量周期一致",true,{"key":16,"text":17,"correct":18},"B","按期中结算价款总额计，支付比例不高于60%",false,{"key":20,"text":21,"correct":18},"C","进度款支付不用扣除甲供材金额",{"key":23,"text":24,"correct":18},"D","承包人应在每个计量周期到期后的14天内向发包人提交已完工程进度款申请","考点:进度款。发包人提供的甲供材料金额，应按照发包人签约提供的单价和数量从进度款支付中扣出，列入本周期应扣减的金额中。进度款的支付比例按照合同约定，按期中结算价款总额计，不低于60%，不高于90%。承包人应在每个计量周期到期后的7天内向发包人提交已完工程进度款申请。参见教材P195。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]