[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107635,783,1,"单选题","发包人应在收到承包人进度款支付申请后的（ ）天内，根据计量结果和合同约定对申请内容予以核实，确认后向承包人出具进度款支付证书。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","考点:进度款。根据《计价规范》规定，发包人应在收到承包人进度款支付申请后的14天内，根据计量结果和合同约定对申请内容予以核实，确认后向承包人出具进度款支付证书；发包人应在签发进度款支付证书后的14天内，按照支付证书列明的金额向承包人支付进度款。发包人向承包人支付的比例，应为期中结算价款总额的60%～90%。参见教材P196。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]