[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107634,783,1,"单选题","某工程承包合同总额为9000万元，主要材料及构件所占比重为60%，工程预付款为合同总额的20%，则工程预付款的起扣点为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1800",false,{"key":16,"text":17,"correct":14},"B","3600",{"key":19,"text":20,"correct":14},"C","5400",{"key":22,"text":23,"correct":24},"D","6000",true,"考点:预付款。根据起扣点的计算公式，该工程预付款的起扣点＝合同总额－预付款\u002F主要材料及构件所占比重＝9000－（9000×20%）\u002F60%＝6000（万元）。参见教材P195。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]