[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107631,783,1,"单选题","在《标准施工招标文件》合同条款中，承包商只可以获得费用补偿的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人要求承包人提前竣工",true,{"key":16,"text":17,"correct":18},"B","发包人原因引起的暂停施工",false,{"key":20,"text":21,"correct":18},"C","发包人原因造成工期延误",{"key":23,"text":24,"correct":18},"D","发包人原因导致试运行失败","考点:索赔费用的计算。发包人要求承包人提前竣工，承包人只能索赔费用。选项B、C，承包人可索赔工期、费用和利润。选项D，承包人可索赔费用和利润。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]