[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107630,783,1,"单选题","下列事件中，需要进行现场签证的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同范围以内零星工程的确认",false,{"key":16,"text":17,"correct":18},"B","修改施工方案引起工程量增减的确认",true,{"key":20,"text":21,"correct":14},"C","承包人原因导致设备窝工损失的确认",{"key":23,"text":24,"correct":14},"D","合同范围以外新增工程的确认","考点:现场签证。现场签证的范围一般包括：适用于施工合同范围以外零星工程的确认；在工程施工过程中发生变更后需要现场确认的工程量；非承包人原因导致的人工、设备窝工及有关损失；符合施工合同规定的非承包人原因引起的工程量或费用增减；确认修改施工方案引起的工程量或费用增减；工程变更导致的工程施工措施费增减等。参见教材P191。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]