[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107628,783,1,"单选题","对于因异常恶劣的气候造成施工单位的施工机械损坏和人员窝工以及相应的费用索赔，监理工程师应当（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","批准相应的施工机械损坏和人员窝工费用",false,{"key":16,"text":17,"correct":14},"B","批准相应的人工、材料、机具费",{"key":19,"text":20,"correct":14},"C","批准相应的措施项目费",{"key":22,"text":23,"correct":24},"D","不予批准",true,"本题考查索赔的主要类型。遇到发包人无法预见的情况，例如特殊反常天气并造成不利影响，承包人可以得到延长工期，但无法获得费用补偿。参见教材P182。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]