[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107625,783,1,"单选题","根据计价规范规定，发包人应在收到承包人的现场签证报告后的（ ）内进行核实，给予确认或提出修改意见。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","24小时",false,{"key":16,"text":17,"correct":18},"B","48小时",true,{"key":20,"text":21,"correct":14},"C","7天",{"key":23,"text":24,"correct":14},"D","14天","考点:现场签证。承包人应在收到发包人指令后的7天内，向发包人提交现场签证报告；发包人应在收到承包人的现场签证报告后的48小时内进行核实，给予确认或提出修改意见（预期，视为被认可）。参见教材P191。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]