[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107622,783,1,"单选题","某工程的招标控制价为800万元，中标人的投标报价为777万元，施工图预算造价为780万元，则承包人的报价浮动率为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.04%",false,{"key":16,"text":17,"correct":14},"B","2.50%",{"key":19,"text":20,"correct":21},"C","2.88%",true,{"key":23,"text":24,"correct":14},"D","2.96%","考点:工程变更价款的确定方法。根据招标工程承包人报价浮动率的计算公式，则有本工程的报价浮动率L＝（1-中标价\u002F招标控制价）×100%＝（1－777\u002F800）×100%＝2.875%。参见教材P176。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]