[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107621,783,1,"单选题","某招标项目，承包人报价值为3000万元，经修正后的，发承包双方以均认可的2900万元签约合同。该项目招标控制价位3100万元，承包人施工图预算为3050万元。则承包人报价浮动率是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.64%",false,{"key":16,"text":17,"correct":14},"B","3.22%",{"key":19,"text":20,"correct":14},"C","3.33%",{"key":22,"text":23,"correct":24},"D","6.45%",true,"考点:工程变更价款的确定方法。L＝（1－2900\u002F3100）×100%＝6.45%。参见教材P176。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]