[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107620":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107620,783,1,"单选题","根据《建设工程工程量清单计价规范》GB50500－2013条款，如果工程量偏差和工程变更等原因导致工程量偏差超过（ ）时，可进行合同价款调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":18},"B","15%",true,{"key":20,"text":21,"correct":14},"C","20%",{"key":23,"text":24,"correct":14},"D","25%","考点:工程量偏差。工程量偏差和工程变更等原因导致工程量偏差超过15%时，可进行合同价款调整。新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]