[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107617,783,1,"单选题","在合同价款调整中，出现合同价款调增事项后的（ ）天内，承包人应向发包人提交合同价款调增报告并附上相关资料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","考点:合同价款应当调整的事项及调整程序。出现合同价款调增事项后的14天内，承包人应向发包人提交合同价款调增报告并附上相关资料。参见教材P163。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]