[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107616,783,1,"单选题","某混凝土工程招标工程量为900m3，综合单价为350元\u002Fm3。在施工过程中由于设计变更导致实际完成工程量为1150m3。合同约定：当实际完成工程量增加超过15%时，超出部分的综合单价要调低，调价系数为0.9。该混凝土工程实际结算工程款为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","36.2250",false,{"key":16,"text":17,"correct":14},"B","39.3750",{"key":19,"text":20,"correct":21},"C","39.8475",true,{"key":23,"text":24,"correct":14},"D","40.2500","考点:工程量偏差。工程量增加1150-900=250m3，250\u002F900=27.78%＞15%，该混凝土工程实际结算工程款=900×1.15×350+（1150-900×1.15）×350×0.9=398475（元）=39.8475（万元）。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]