[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107615,783,1,"单选题","某工程项目的招标控制价为400元，投标报价为320元，投标报价浮动率为5%。如果履行合同过程中，其工程量的偏差达到20%，则其综合单价应调整为（ ）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","320",false,{"key":16,"text":17,"correct":18},"B","323",true,{"key":20,"text":21,"correct":14},"C","400",{"key":23,"text":24,"correct":14},"D","460","考点:工程量偏差。根据计价规范，由于工程量偏差致使投标报价与招标控制价的偏差超过15%，而且投标报价P0＝320＜P2×（1-L）×（1-0.15）＝400×95%×0.85＝323，于是调整后新的综合单价（式5-5）应为323（元）；P0＝320＜P2×（1＋0.15）＝400×1.15＝460，选项D不予采纳。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]