[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107612,783,1,"单选题","根据《建设工程工程量清单计价规范》，当承包人投标报价中材料单价低于基准单价时，施工期间材料单价跌幅以（ ）为基础，超过合同约定的风险幅度值的，其超过部分按实调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标报价",true,{"key":16,"text":17,"correct":18},"B","招标控制价",false,{"key":20,"text":21,"correct":18},"C","基准单价",{"key":23,"text":24,"correct":18},"D","实际单价","考点:物价变化。当承包人投标报价中材料单价低于基准单价时，施工期间材料单价跌幅以投标报价为基础，超过合同约定的风险幅度值的，其超过部分按实调整。参见教材P168。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]