[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107611,783,1,"单选题","对于不符合合同文件要求的工程，承包人超出施工图纸范围或因承包人原因造成返工的工程量，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不予计量",true,{"key":16,"text":17,"correct":18},"B","酌情计量",false,{"key":20,"text":21,"correct":18},"C","全部计量",{"key":23,"text":24,"correct":18},"D","减半计量","考点:工程计量的原则。对于不符合合同文件要求的工程，承包人超出施工图纸范围或因承包人原因造成返工的工程量，不予计量。参见教材P160。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]