[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107607,783,1,"单选题","根据《建设工程施工合同（示范成本）》GF－2017－0201，监理人应在收到承包人提交的工程量报告后（ ）天内，完成对工程量报表的审核并发送发包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","14",false,{"key":20,"text":21,"correct":18},"C","21",{"key":23,"text":24,"correct":18},"D","28","考点:单价合同的计量。监理人应在收到承包人提交的工程量报告后7天内完成对承包人提交的工程量报表的审核并报送发包人。参见教材P161。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]