[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107603,783,1,"单选题","根据某工作单位时间内的实物工程量、投入资源量，计算某时刻的投资额、计划累计完成投资额，并标注在时标网络图上，可以得到（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按时间进度分解的资金使用计划",true,{"key":16,"text":17,"correct":18},"B","按子项目分解的资金使用计划",false,{"key":20,"text":21,"correct":18},"C","正态分布曲线",{"key":23,"text":24,"correct":18},"D","S形曲线","考点:资金使用计划编制。编制按时间进度的资金使用计划，通常可利用控制项目进度的网络图进一步扩充而得。即在建立网络图时，一方面确定完成各项活动所需花费的时间，另一方面同时确定完成这一活动的合适的投资支出预算。参见教材P158。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]