[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107595,783,1,"单选题","工程质量形成过程中，（ ）阶段对工程质量的影响主要是确定工程项目应达到的质量目标和水平。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","项目可行性研究",{"key":19,"text":20,"correct":14},"C","项目策划",{"key":22,"text":23,"correct":24},"D","项目决策",true,"考点:工程建设阶段对质量形成的作用与影响。项目决策阶段对工程质量的影响主要是确定工程项目应达到的质量目标和水平。参见教材P2",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]