[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107590,783,1,"单选题","根据《建设工程质量管理条例》，建设单位在申领施工许可证之前，应当按照有关规定办理（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开工报告手续",false,{"key":16,"text":17,"correct":14},"B","监理单位的委托手续",{"key":19,"text":20,"correct":14},"C","保证安全施工措施的审批手续",{"key":22,"text":23,"correct":24},"D","工程质量监督手续",true,"考点:工程质量管理主要制度。申请领取施工许可证，应当具备下列条件：经办理该建筑工程用地批准手续；在城市规划区的建筑工程，已经取得规划许可证；需要拆迁的，其拆迁进度符合施工要求；已经确定建筑施工企业；有满足施工需要的施工图纸及技术资料；有保证工程质量和安全的具体措施；建设资金已经落实；法律、行政法规规定的其他条件。参见教材P8。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]