[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107574,783,1,"单选题","建设工程活动中，（ ）的质量控制，主要是通过项目的可行性研究，选择最佳建设方案，使项目的质量要求符合业主的意图，并与投资目标相协调，与所在地区环境相协调。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","决策阶段",true,{"key":16,"text":17,"correct":18},"B","施工阶段",false,{"key":20,"text":21,"correct":18},"C","监理阶段",{"key":23,"text":24,"correct":18},"D","勘察设计阶段","考点:工程质量控制主体。决策阶段的质量控制，主要是通过项目的可行性研究，选择最佳建设方案，使项目的质量要求符合业主的意图，并与投资目标相协调，与所在地区环境相协调。参见教材P4。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]