[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107550,783,1,"单选题","（ ）收到建设工程竣工报告后，应当组织设计、施工、工程监理等有关单位进行竣工验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","施工单位",{"key":23,"text":24,"correct":14},"D","质量监督机构","考点:工程质量管理主要制度。竣工验收是建设单位组织，并自工程竣工验收合格起15日内，向工程所在地县级以上地方人民政府建设行政主管部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]