[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107523":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107523,783,1,"单选题","检验批质量验收时，主控项目必须全部符合有关（ ）的规定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程监理规范",false,{"key":16,"text":17,"correct":14},"B","工程技术规程",{"key":19,"text":20,"correct":21},"C","专业验收规范",true,{"key":23,"text":24,"correct":14},"D","质量验收统一标准","考点:建筑工程施工质量验收程序和合格规定。主控项目是对检验批的基本质量起决定性影响的检验项目，是保证工程安全和使用功能的重要检验项目，必须从严要求，因此必须全部符合有关专业验收规范的规定。参见教材P162。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]