[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107518,783,1,"单选题","下列关于城市轨道交通工程的验收表述不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位工程验收合格且通过相关专项验收后，方可组织项目工程验收",false,{"key":16,"text":17,"correct":18},"B","项目工程验收合格后，建设单位应组织不载客试运行，试运行一个月.并通过全部专项验收后，方可组织竣工验收",true,{"key":20,"text":21,"correct":14},"C","竣工验收合格后，城市轨道交通建设工程方可履行相关试运营手续",{"key":23,"text":24,"correct":14},"D","城市轨道交通建设工程验收分为单位工程验收.项目工程验收.竣工验收三个阶段","考点:单位工程验收。城市轨道交通建设工程验收分为单位工程验收、项目工程验收、竣工验收三个阶段。城市轨道交通建设工程所包含的单位工程验收合格且通过相关专项验收后，方可组织项目工程验收；项目工程验收合格后，建设单位应组织不载客试运行，试运行三个月、并通过全部专项验收后，方可组织竣工验收；竣工验收合格后，城市轨道交通建设工程方可履行相关试运营手续。参见教材P181。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]