[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107517,783,1,"单选题","下列关于城市轨道交通工程单位工程验收的内容和程序描述不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","检查单位工程实体质量时涉及运营及使用功能的部位应全数检测",true,{"key":16,"text":17,"correct":18},"B","检查施工单位自检报告及施工技术资料时包含主要产品的质量保证资料及合格报告",false,{"key":20,"text":21,"correct":18},"C","建设.勘察.设计.施工.监理等单位分别汇报工程合同履约情况和在工程建设各个环节执行法律.法规和工程建设强制性标准的情况",{"key":23,"text":24,"correct":18},"D","工程质量监督机构出具验收监督意见","考点:单位工程验收。选项A中关于检测单位工程实体质量时涉及运营安全及使用功能的部位应进行抽样检测，而不是进行全数检测。参见教材P182。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]