[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107514,783,1,"单选题","下列关于城市轨道交通工程项目工程验收的内容和程序表述不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","各验收小组实地查验工程质量，复查单位工程验收遗留问题的整改情况",false,{"key":16,"text":17,"correct":14},"B","验收组对工程勘察.设计.施工.监理.设备安装质量等方面进行评价，审查对试运行有影响的相关专项验收情况",{"key":19,"text":20,"correct":21},"C","城市轨道交通建设工程自竣工验收合格之日起可投入不载客试运行，试运行时间不应少于三个月",true,{"key":23,"text":24,"correct":14},"D","审查系统设备联合调试情况，签署项目工程验收意见","考点:项目工程验收。选项C应该是城市轨道交通建设工程自项目工程验收合格之日起可投入不载客试运行，试运行时间不应少于三个月。参见教材P183。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]