[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107513,783,1,"单选题","下列关于城市轨道交通工程竣工验收的内容和程序的描述不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位汇报试运行情况",false,{"key":16,"text":17,"correct":18},"B","建设单位应在竣工验收合格之日起7个工作日内，将竣工验收报告和相关文件，报城市建设主管部门备案",true,{"key":20,"text":21,"correct":14},"C","验收委员会质询相关单位，讨论并形成验收意见",{"key":23,"text":24,"correct":14},"D","验收委员会签署工程竣工验收报告，并对遗留问题做出处理决定","考点:竣工验收。选项B中应该是建设单位应在竣工验收合格之日起15个工作日内，将竣工验收报告和相关文件，报城市建设主管部门备案。参见教材P183～P184。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]