[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107510":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107510,783,1,"单选题","当个别检验批发现问题，难以确定能否验收时，应请具有资质的法定检测单位进行检测鉴定。当鉴定结果认为能够达到设计要求时，该检验批（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重新进行验收",false,{"key":16,"text":17,"correct":18},"B","可予以验收",true,{"key":20,"text":21,"correct":14},"C","按技术处理方案和协商文件的要求予以验收",{"key":23,"text":24,"correct":14},"D","不予验收","考点:建筑工程质量验收时不符合要求的处理。当个别检验批发现问题，难以确定能否验收时，应请具有资质的法定检测单位进行检测鉴定。当鉴定结果认为能够达到设计要求时，该检验批可以通过验收。参见教材P180。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]