[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107501,783,1,"单选题","下列关于检验批质量验收合格的规定中，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主控项目的质量经全数检验均应合格",true,{"key":16,"text":17,"correct":18},"B","主控项目是对检验批的基本质量起决定性影响的检验项目",false,{"key":20,"text":21,"correct":18},"C","工程材料.构配件和设备的技术性能属于主控项目",{"key":23,"text":24,"correct":18},"D","一般项目的质量经抽样检验合格","考点:建筑工程施工质量验收程序和合格规定。选项A错误，主控项目的质量经抽样检验均应合格。参见教材P162。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]