[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107494,783,1,"单选题","分项工程质量验收时，（ ）对施工单位所报资料逐项进行审查，符合要求后签认分项工程报审表、报验表及质量验收记录。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",false,{"key":16,"text":17,"correct":18},"B","专业监理工程师",true,{"key":20,"text":21,"correct":14},"C","监理员",{"key":23,"text":24,"correct":14},"D","建设单位","考点:分项工程质量验收。分项工程质量验收时，专业监理工程师对施工单位所报资料逐项进行审查，符合要求后签认分项工程报审表、报验表及质量验收记录。参见教材P164。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]