[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107477,783,1,"单选题","在施工过程中，当分部工程达到验收条件时，应由（ ）组织验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","施工单位项目负责人",{"key":23,"text":24,"correct":14},"D","建设单位现场代表","考点:建筑工程施工质量验收程序和合格规定。分部工程应由总监理工程师组织施工单位项目负责人和项目技术负责人等进行验收。参见教材P166。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]