[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107476":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107476,783,1,"单选题","单位工程验收时，对主要功能还须进行抽查，抽查项目是在检查资料文件的基础上由（ ）商定。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理和建设单位",false,{"key":16,"text":17,"correct":14},"B","施工和设计单位",{"key":19,"text":20,"correct":14},"C","设计和建设单位",{"key":22,"text":23,"correct":24},"D","参加验收的各方人员",true,"考点:建筑工程施工质量验收程序和合格规定。主要使用功能抽查项目是在检查资料文件的基础上由参加验收的各方人员商定，并用计量、计数的方法抽样检验，检验结果应符合有关专业验收规范的规定。参见教材P171。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]