[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107472":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107472,783,1,"单选题","建筑工程施工质量验收中，经返工重做或更换器具、设备的检验批，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","予以验收",false,{"key":16,"text":17,"correct":18},"B","重新进行验收",true,{"key":20,"text":21,"correct":14},"C","鉴定验收",{"key":23,"text":24,"correct":14},"D","协商验收","考点:建筑工程质量验收时不符合要求的处理。建筑工程施工质量不符合要求，经返工重做或更换器具、设备检验批，应重新进行验收。参见教材P180。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]